Tuesday, August 20, 2013

August 20 th Update

The pieces are coming together. 

Thursday, August 15, 2013

August 15

Library storefronts are in. Glass is coming tomorrow. The rug is going down too.  

Wednesday, August 14, 2013

August 14

A busy day here. Railing is taking shape. Carpet ready to go in library. Very cool new lights. Team USA floor going down. 

Monday, August 12, 2013

August 12

New railing is going in. Cafeteria floor is beautiful. 

Friday, August 9, 2013

August 9th Update

Floors, ceilings and lighting are looking good. 

Friday, August 2, 2013

August 2nd.

Things are starting to come together. Library ceiling and lights. The bleachers.  The cafeteria ceiling and lights. 

 

Tuesday, July 23, 2013

Friday, July 19, 2013

Tuesday, July 16, 2013

Monday, July 15, 2013

July 15 Update

New floors are going in. New pavement is poured and lighting bases are in. New ceilings are going up. 

Friday, July 12, 2013

July 12th update!







Monday, July 8, 2013

July 8th Update

Library is taking shape. Cafeteria floor is up and vents are filled.